We began the new year with the roof sealing. Interesting process of seven layers of sealer, asphalt, fiberglass, and aluminum paint.

We are still plastering and stuccoing -- seems like that will go on forever.

Click here for this week’s website update: http://rollybrook.com/01-03.htm

Rolly Pirate

E-visit me http://Rollybrook.com
On Facebook as Rolly Brook



keith

Jan 4, 2003, 10:05 PM

Post #2 of 3 (1083 views)

Shortcut

Re: [Rolly] House Project Update for 03 January 2003

Can't Post |
looks good, Rolly. I hope you get more mileage out of the aluminum paint than we did. Our temperature extremes are pretty severe, but we were only getting about a year out of a coat of the aluminum paint before it all flaked off. I've had better luck with something called "snow roof," a very heavy duty latex paint that has some stretch in it.


Uncle Jack


Jan 5, 2003, 4:15 AM

Post #3 of 3 (1105 views)

Shortcut

Mirador??

Can't Post | Private Reply
Rolly;

It looks as if there is a lot of usable space on the roof..........any plans for a mirador or a palapa?

UJ

(This post was edited by Uncle Jack on Jan 5, 2003, 4:16 AM)
 
 
 