Building Project Update for 27 December 2003
|
Can't Post | Private Reply
|
We're almost done! Probably another week inside and then a few days to build new sidewalks. Then I can sleep late if my dogs will let me. Who knows when the cabinet work will be done. This week we completed the painting and got about half of the electrical finish work done. We're 2/3 done with floor tile. Pretty good for a 3-day week. We had an extra worker this week -- Gabriel, one of the Las Casas owners, had vacation this week, so he worked with us. A few new pictures at http://rollybrook.com/R03-12-27.htm Happy new year! Rolly E-visit me http://Rollybrook.com On Facebook as Rolly Brook
|