Building Project Update for 22 March 2003
|
Can't Post | Private Reply
|
We are about 80% done with the floor tile in the two apartments in the north building. Work on installing the water tanks and pumps continues. We're still waiting for Coco to complete the windows for his house so we can get moving on it. The new cabinet maker we had lined up fell through -- the job he has been working on got bigger, so he couldn't work for us. Enrique found another guy, Roberto, who says he has no other jobs to interfere with working fulltime on our project. I hope! There is no webpage update yet because my web server is having technical problems. My site can be viewed, but not updated. I'll let you know when it is ready. Stay tuned. Rolly
|